Construction underway at Prairie du Chien High School

Error message

  • Warning: array_merge(): Expected parameter 1 to be an array, bool given in _simpleads_render_ajax_template() (line 133 of /home/pdccourier/www/www/sites/all/modules/simpleads/includes/simpleads.helper.inc).
  • Notice: Trying to get property 'settings' of non-object in _simpleads_adgroup_settings() (line 343 of /home/pdccourier/www/www/sites/all/modules/simpleads/includes/simpleads.helper.inc).
  • Warning: array_merge(): Expected parameter 1 to be an array, bool given in _simpleads_render_ajax_template() (line 157 of /home/pdccourier/www/www/sites/all/modules/simpleads/includes/simpleads.helper.inc).
  • Notice: Trying to access array offset on value of type null in include() (line 24 of /home/pdccourier/www/www/sites/all/modules/simpleads/templates/simpleads_ajax_call.tpl.php).

Excavation and the installation of footings has begun on the east side of Prairie du Chien High School. The gymnasium and greenhouse addition will be 31,170 square feet. (Photos by Luke Lucas)

A rooftop view of the construction shows busy crews moving earth. (Photo by Luke Lucas)

By Ted Pennekamp

 

Construction has begun on the $18.9 million facilities upgrade project that will involve Prairie du Chien High School, Bluff View Intermediate School and B. A. Kennedy Elementary School.

A fence was placed around the front parking lot at the high school several weeks ago for a staging area for construction materials and equipment. Recently, excavation work, along with the installation of footings has begun on the east side of the high school. High School and B. A. Kennedy Head of Maintenance Luke Lucas said the work is in preparation for the construction of three gymnasiums and a greenhouse. 

Lucas said the gymnasiums and greenhouse will take up 31,170 square feet.

As soon as the excavation and footings work is done for the gymnasiums and greenhouse, construction crews will start doing the same thing on the area for the new auditorium, said Lucas. The new auditorium will be on the northwest end of the high school and will be 27,960 square feet.

A groundbreaking ceremony was held at the high school at noon on Wednesday, April 19.

Olympic Builders of Holmen is the general contractor for the project. August or September of 2018 is the scheduled completion time and occupancy plan.

The general overall project involves construction of a new 750-seat auditorium, a new greenhouse, new gymnasiums and support space at the high school; and a gym annex, support space, instrumental music space and technical education space at Bluff View. There will also be playground improvements at Bluff View, along with parking improvements and site upgrades. At B. A. Kennedy, there will be remodeling, renovation and other improvements. Some of the highlights at B. A. Kennedy include numerous upgrades to the library and upgrades to a first grade restroom.